Name Tintsfield Gathering Pilot, Narrabri Qld
Value $500,000 - $1 million
Client Eastern Star Gas
Scope Installation of Gas (250mm) and Water (200mm) Coal Seam Gas Gathering piping from the 6 wells of the ESG Tinstfield Pilot to the tie-in on the existing steel gas line running to the Wilga Park Power Station. The project was another successful major project for ESG under the current 5yr service agreement. The project was not straightforward and included installation of a 110mm Water re-injection line, fuel Gas lines for Gas Generators, Electrical Cable, installation of 7 LPD's, 7 HPV's, 7 Injection Points and 2 road crossings and multiple services.
Key Features